3 GA Grace
Home Projects Halyard Wharf Apartments — Stage 2 Requirements

Project stages

Completed Current Upcoming
  1. Development approval 14 Mar 2026
  2. CC Construction certificate Due 18 Nov 2026
  3. CW Construction 30 Jun 2027
  4. OC Occupation certificate 22 Sep 2027
  5. HO Handover 15 Oct 2027
Active 38Watching 6All 52
Search requirements… Status 2
Required itemStatusOwnerActivityDue dateAction
Structure 4 items
1 accepted · 1 in review · 1 rework
ST-03
Structural engineer's certificate — Level 3 transfer slab
Design certificate for the post-tensioned transfer slab, signed by the engineer of record.
Structural Engineer
Under review
AF Ana
3 2
Due in 2 days
ST-04
Pre-pour inspection record, ground floor slab and footings
Photos and the signed inspection checklist before each pour.
Accepted
JP Joel
1 6
4 Nov, 2026
Done
ST-07
Geotechnical report — bearing capacity and site classification
Elise Marangoni The report covers the Stage 1 lots only. Upload the Stage 2 addendum.
Structural
Rework
AFRI
5 1
2 days overdue
ST-09
Shop drawings — structural steel canopy over the retail entry, rev C
Unassigned––No due date
Fire safety 5 items
0 accepted · 2 in review · 0 rework
FS-02
Fire engineering brief and performance solution — basement carpark
Performance solution for the extended travel distance on B2, with the peer review letter.
Fire Performance solution Peer review +1
Under review
BOGA +1
8 4
Due today
FS-07
Fire damper installation certificate (AS 1668.1)
Uploaded, not in review
MS Mateo
1
Due in 5 days
FS-11
Hydrant and sprinkler system commissioning report
Fire Hydraulic
Awaiting upload
MS Mateo
–12 Dec, 2026
FS-12
Penetration sealing schedule with product data sheets and photos
Draft approved
BO Bridget
2 3
28 Nov, 2026
FS-15
Emergency lighting and exit sign installation certificate
Awaiting upload
JT Jess
–9 Dec, 2026
Council conditions 4 items
2 accepted · 0 in review · 1 rework
CC-41
Condition 41 — dilapidation report for neighbouring lots 7 and 9
Accepted
GA Grace
2 2
21 Oct, 2026
Done
CC-44
Section 7.12 contributions payment receipt
Accepted
JP Joel
1
18 Oct, 2026
Done
CC-52
Construction traffic management plan, approved by council
Elise Marangoni The approved plan is missing the loading zone. Re-upload the council-stamped copy.
Rework
GA Grace
4 2
5 days overdue
CC-58
Sediment and erosion control plan sign-off
Awaiting upload
RI Ravi
–Due in 3 days
Services and hydraulics 6 items
0 accepted · 1 in review · 0 rework